Thursday, March 26, 2009
March 26, 2009Met with Roger Jarrett of DVPE to discuss progress on the new Middle School and High School remodel as follows:High School
1. June 8 is bid date - they are currently working on drawings and will meet scheduled dates
2. We discussed the construction on possible air conditioning of prebuilt band practice rooms.
3. Equipment rooms have been located as follows;a. VAV air handler for band areab. VAV air handler for office area
4. Discussed including connecting pool heat in JR HS to DHRC chiller
5. Discussed adding fan coil unit to the server area currently served by Zone 10 of AHU 13 in the high school
6. Wet side economizer and condenser warm up in the bid.
7. Roger will visit the job Friday 3/27 and will contact Jim Bachman for some guidance in the building.New MS1. Reiterated the problems with the 2200 cfm Temspec units at the high school2. There are some large computer rooms in the new building which must be considered.T
Posted by Kurt Stevens
Saturday, March 14, 2009
Signing in to initiate blog responses. Will continue contact with VPDE this week to continue working on pre bid commissioning. We have discussed the tc issues, the problem with Temspec 2000 units and wet side economizer for ms remodel and new middle school.Kurt 3/14/09
Posted by Kurt Stevens at 12:54 PM 0 comments